P.S. 270
234 Street & Merrick Blvd.
Laurelton, NY
Design and construction of a primary school for approx 704 students. The building will be a four-story structure with a full cellar and mechanical penthouse and have an approx total gross area of 95,500 sf. . .
|
|
|
|
|
|
|
|
|
| $2,462,000.00 |
Far Rockaway H.S.
C000009625
|
|
|
NYC School Construction Authority
|
High School Restructure, accelerated project to be completed in 82 days |
| $5,280,000.00 |
Francis Lewis H.S.
C000009546
|
|
|
NYC School Construction Authority
|
Windows & Gym Upgrade |
| $7,889,000.00 |
P.S. 150X
C000009592
|
|
|
NYC School Construction Authority
|
Exterior Modernization, Electrical Upgrade & Playground |
| $4,795,000.00 |
DOE Queens Supt. Office
C000009647
|
|
|
NYC School Construction Authority
|
Repair underground parking garage ceiling leakage |
| $58,439,000.00 |
Brooklyn College New West Quad Building
|
|
|
Dormitory Authority of the State of New York
|
A new 140,000-sq.-ft. West Quad Building will include classroom space and house admissions, recruitment, financial aid, food services and grounds and custodial support offices. It will also be home to the Department of Physical Education & Exercise Science and feature improved indoor sports facilities including several new gymnasiums, a swimming pool and an indoor track. |
| $4,089,000.00 |
Family Court HS
|
|
|
NYC School Construction Authority
|
Interior Demolition |
$19,187,000.00
|
PS 245Q
|
|
|
NYC School Construction Authority
|
Three Story New Building Early Childhood Center |
$56,587,000.00
|
PS 237K |
|
|
NYC School Construction Authority
|
New Primary School |
| $22,148,000.00 |
PS 829R
|
|
|
NYC School Construction Authority
|
Addition to & Rehabilitation of Existing School. |
| $5,001,000 |
Jamaica Station
Queens, NY.
LIRR Contract No. 5916
|
Jamaica Central Control Building – Interior Fit Out Construction |
|
Long Island Railroad
90-27 Sutphin Ave.
Jamaica, NY 11435
|
Fit Out Construction of New Office Space at the station’s central control building; Perimeter & partition walls; Interior finishes; Floor Coverings and access flooring; Operable partitions; a ceiling panel system; window treatments; doors & locks; a security system; lighting and mechanical distribution system/integration with the base building system, including connection to this system; a fire sprinkler system extension; electrical wiring; switches and receptacles; fire alarm system installation; and communication system installation and integration. |
| $2,462,000 |
Far Rockaway H.S.
C000009625
|
High School Restructure, accelerated project to be completed in 82 days |
|
NYC School Construction Authority
|
|
| $5,280,000 |
Francis Lewis H.S.
C000009546
|
Windows & Gym Upgrade |
|
NYC School Construction Authority
|
|
| $7,889,000 |
P.S. 150X
C000009592
|
Exterior Modernization, Electrical Upgrade & Playground |
|
NYC School Construction Authority
|
|
| $4,795,000 |
DOE Queens Supt. Office
C000009647
|
Repair underground parking garage ceiling leakage |
|
NYC School Construction Authority
|
|
| $58,439,000
|
|
|
|
Brooklyn College New West Quad Building
|
A new 140,000-sq.-ft. West Quad Building will include classroom space and house admissions, recruitment, financial aid, food services and grounds and custodial support offices. It will also be home to the Department of Physical Education & Exercise Science and feature improved indoor sports facilities including several new gymnasiums, a swimming pool and an indoor track. |
|
|
|
|
|
|